Manchester Public Schools Capital Improvement Plan
2006-2007 Through 2013-2014
SUMMARY BY FUNDING SOURCE
SCHOOL PROJECT 2006/07 2007/08 2008/09 2009/10 2010/11 2011/12 2012/13 2013/14 FUNDING SOURCE
Like New/1 Yr  HP(10) NH(8) Wash(2) Verpl(4) Robt(7) Martin(9) Buckley(3) Keeney(6)
                   
Bennet Interior Painting Lead Abatement                   CURRENT BOND
Bennet Replace Stair Treads and Risers                   CURRENT BOND
Bennet Area of Refuge     REFERENDUM
 
            CURRENT BOND
Bennet Electronic Door Opener                   CURRENT BOND
Bennet Ramps (Barnard & Rec)                   CURRENT BOND
Bennet Handicapped Restroom (all bldgs)                   CURRENT BOND
Bennet Chimney                   CURRENT BOND
Bennet Fire Escape Stairs Rec & Cheney                   CURRENT BOND
Bennet Asbestos Abatement                   CURRENT BOND
Bennet Window Replacement                   CURRENT BOND
Bennet Ventilation Improvement HVAC                   CURRENT BOND
Bennet Oil Fat Separator                   CURRENT BOND
Bennet Roof Rec Building                   CURRENT BOND
Bennet Electrical Distribution                   CURRENT BOND
Bennet Fire Alarm Replacement                   CURRENT BOND
Bennet Rec Building Gym Acoustics                   CURRENT BOND
Bennet Elevator Barnard                   CURRENT BOND
                   
Bentley Roof Replacement (shingled only)                     CHEFA/New Blg
Bentley Fire Alarm Replacement       NEW BUILDING
 
            CHEFA/New Blg
Bentley Sprinkler System                     CHEFA/New Blg
Bentley Boiler Replacement                     CHEFA/New Blg
Bentley Asbestos Abatement                     CHEFA/New Blg
Bentley Lead Abatement                     CHEFA/New Blg
Bentley Window Replacement                     CHEFA/New Blg
Bentley Data Wiring                     CHEFA/New Blg
Bentley Elevator                      CHEFA/New Blg
                   
                   
Central Office Facility Inventory    100,000               Board Reserve
Total for Board Reserve     100,000 0 0 0 0 0 0 0  
                   
Bowers Oil Fat Separator   15,000               Cafeteria Funds
Buckley Oil Fat Separator           15,000       Cafeteria Funds
Illing Oil Fat Separator     15,000             Cafeteria Funds
Keeney Oil Fat Separator         15,000         Cafeteria Funds
Martin Oil Fat Separator             15,000     Cafeteria Funds
Robertson Oil Fat Separator           15,000       Cafeteria Funds
Waddell Oil Fat Separator   15,000               Cafeteria Funds
Total for Cafeteria      30,000 15,000 0 15,000 30,000 15,000 0 0  
                   
Bowers AC Media Center           25,000       Future Bond
Bowers Chimney           58,000       Future Bond
Bowers Electrical Upgrade           65,000       Future Bond
Bowers Roof Replacement           669,375       Future Bond
Buckley Convert Kitchen to Natural Gas               100,000   Future Bond
Buckley Tunnel Asbestos Abatement               150,000   Future Bond
Buckley Like New Renovation               13,765,680   Future Bond
Central Office Install elevator   250,000               Future Bond
Highland Park Like New Renovation   6,276,060               Future Bond
Highland Park Roof Replacement   273,000               Future Bond
Illing Window Replacement   710,000               Future Bond
Keeney Like New Renovation                 12,044,880 Future Bond
Martin Roof Replacement   525,000               Future Bond
Martin Like New Renovation             8,423,980     Future Bond
MRA General Addition (3-4 classrooms)           456,250       Future Bond
Nathan Hale Like New Renovation     10,354,260             Future Bond
Nathan Hale Elevator Cylinder     40,000             Future Bond
Robertson Like New Renovation           11,083,701       Future Bond
Verplanck Like New Renovation         12,529,220         Future Bond
Waddell Renovate Space Computer Lab           20,000       Future Bond
Waddell AC Media Center           25,000       Future Bond
Waddell Replace Ceiling           50,000       Future Bond
Waddell Boiler Replacement           250,000       Future Bond
Waddell Roof Replacement           312,500       Future Bond
Waddell Electrical Upgrade     60,000             Future Bond
Washington Like New Renovation       13,563,960           Future Bond
Total for Future Bond     8,034,060 10,454,260 13,563,960 12,529,220 13,014,826 8,423,980 14,015,680 12,044,880  
                   
Systemwide Vehicle Capital Replacement   111,000 85,000 110,000 130,000 110,000 110,000 110,000 110,000 Future Lease
Total for Future Lease     111,000 85,000 110,000 130,000 110,000 110,000 110,000 110,000  
                   
Bowers Replace Heating Coil Gym               100,000   Operating Bud
Bowers Replace PA/Clock System     20,000             Operating Bud
Bowers Security Alarm System   10,000               Operating Bud
Bowers Chimney Restoration   24,000               Operating Bud
Bowers Main Entrance - Buzzer   3,000               Operating Bud
Bowers Paving Parking Lot         25,000         Operating Bud
Buckley Install kiln room               15,000   Operating Bud
Buckley Bus Loop     85,000             Operating Bud
Central Office Asbestos Abatement         22,000         Operating Bud
Central Office Repoint             100,000     Operating Bud
Central Office Sprinkler System               90,000   Operating Bud
Central Office Air Conditioning                 250,000 Operating Bud
Central Office Electrical Distribution             30,000     Operating Bud
Highland Park Security Alarm System         10,000         Operating Bud
Highland Park Bus Loop & Parking Lot       85,000           Operating Bud
Illing Gas Burners         20,000         Operating Bud
Illing Chimney     42,000             Operating Bud
Illing Full Camera System           46,465       Operating Bud
Keeney Chimney Repoint top 14 courses   4,500               Operating Bud
Keeney Reroute underground water lines         20,000         Operating Bud
Keeney Replace fire alarm   125,000               Operating Bud
Keeney Paving Parking Lot             25,000     Operating Bud
Martin Chimney     16,000             Operating Bud
Martin Security Alarm System         10,000         Operating Bud
Martin Wheelchair lift Stage         8,000         Operating Bud
Martin Gym           100,000       Operating Bud
MHS Resurface Track         60,000         Operating Bud
MHS G47 Unit Ventilator           100,000       Operating Bud
MHS Elevator Cylinder       75,000           Operating Bud
MHS Weight Room       100,000           Operating Bud
MHS Second Floor Camera Upgrade     17,000             Operating Bud
MHS Parking Lot         75,000         Operating Bud
MRA Replace fire alarm   70,000               Operating Bud
MRA Replace PA/Clock System     10,000             Operating Bud
Nathan Hale Exhaust Fans     40,000             Operating Bud
Robertson Security Alarm System       10,000           Operating Bud
Verplanck Replace PA/Clock System         20,000         Operating Bud
Verplanck A/C & Ventilation Nurses Office   9,000               Operating Bud
Waddell Replace two Unit Ventilators Café   12,000