Capital Improvement Plan              
    FY2006-2007 through FY2013-2014              
                   
Department/Division:   Board of Education/Buckley              
                   
Project Name:   Kitchen Conversion              
                   
Funding Source:   Future Bond              
                   
Project Description & Purpose:   Conver Kitchen to Natural Gas              
                   
Project   Financing Schedule
                   
    2006-2007 2007-2008 2008-2009 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014
                   
Planning & Engineering                         10,000  
                   
Property Acquisition                  
                   
Construction                         10,000  
                   
Equipment                         80,000  
                   
Other                  
                   
Total   0 0 0 0              -   0         100,000 0
Justification/Comments: Current electric hood is not code compliant and is expensive to use.  Recommend that 
kitchen be piped for natural gas and hood, oven & steam tray be replaced with natural
gas appliances.
     
Est. Cost     100,000
Est Reimb (62.56%) (62,560)