Capital Improvement Plan |
|
|
|
|
|
|
|
| |
|
FY2006-2007 through FY2013-2014 |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Department/Division: |
|
Board of Education/Buckley |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Project
Name: |
|
Asbestos Abatement |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Funding
Source: |
|
Future Bond |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Project
Description & Purpose: |
|
Abate Portion of Tunnel Area |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Project |
|
Financing Schedule |
| |
|
|
|
|
|
|
|
|
|
| |
|
2006-2007 |
2007-2008 |
2008-2009 |
2009-2010 |
2010-2011 |
2011-2012 |
2012-2013 |
2013-2014 |
| |
|
|
|
|
|
|
|
|
|
| Planning
& Engineering |
|
|
|
|
|
|
|
2,000 |
|
| |
|
|
|
|
|
|
|
|
|
| Property
Acquisition |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Construction |
|
|
|
|
|
|
|
148,000 |
|
| |
|
|
|
|
|
|
|
|
|
| Equipment |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Other |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Total |
|
0 |
0 |
0 |
0 |
- |
0 |
150,000 |
0 |
|
| Justification/Comments: |
|
Part
of tunnel area must be abated before a kiln room can be added. Kiln project is |
|
scheduled for 2012-2013. Remainder of tunnel abatement scheduled for
2012-2013 Like |
|
New Renovation. |
|
|
|
|
|
|
|
Est. Cost |
|
150,000 |
|
Est Reimb (62.56%) |
(93,840) |
|
Net Cost |
|
56,160 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|