Capital Improvement Plan              
    FY2006-2007 through FY2013-2014              
                   
Department/Division:   Board of Education/Highland Park              
                   
Project Name:   Like - New Renovation              
                   
Funding Source:   Future Bond              
                   
Project Description & Purpose:   Renovate entire facility to certified 20-year useful life              
                   
Project   Financing Schedule
                   
    2006-2007 2007-2008 2008-2009 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014
                   
Planning & Engineering   1,417,482              
                   
Property Acquisition                  
                   
Construction   4,622,331              
                   
Equipment                  
                   
Other   236,247              
                   
Total   6,276,060 0 0 0 0 0 0 0
Justification/Comments: Address building, fire, health and safety code issues.  Includes all aspects of 
construction and FFE.  Excludes ADA code issues.  Costs estimated at $165 
sqft of existing facility, no expansion assumed.  Escalation (Other) calculated
at 5% per year.
Project also to address the following items noted on prior capital improvement plan:
Window Replacement
Install student lockers      
Sprinkler installation Est. Cost           6,276,060
Air Conditioning in media center Est Reimb (62.56%) (3,926,303)
Replace 2 H.B. Smith Boilers (New Section 1965) Net Cost           2,349,757
Install return air units      
Fat, Oil & Grease (FOG) separator (pending legislation)
Classroom furniture