Capital Improvement Plan |
|
|
|
|
|
|
|
| |
|
FY2006-2007 through FY2013-2014 |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Department/Division: |
|
Board of Education/Highland Park |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Project
Name: |
|
Roof Replacement |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Funding
Source: |
|
Future Bond |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Project
Description & Purpose: |
|
Replace Entire Roof |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Project |
|
Financing Schedule |
| |
|
|
|
|
|
|
|
|
|
| |
|
2006-2007 |
2007-2008 |
2008-2009 |
2009-2010 |
2010-2011 |
2011-2012 |
2012-2013 |
2013-2014 |
| |
|
|
|
|
|
|
|
|
|
| Planning
& Engineering |
|
26,000 |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Property
Acquisition |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Construction |
|
234,000 |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Equipment |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Other |
|
13,000 |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Total |
|
273,000 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
| Justification/Comments: |
|
See attached excerpt from K-12
Facilities study completed by Jeter, Cook & Jepson on |
|
June 20, 2002 (item 2.1). It should be noted that SDE Project
#077-0120RR was |
|
|
completed
in 1995 (partial roof replacement) and January 2010 is the earliest date that
the |
|
entire roof will be eligible from
reimbursement (calculated here at 50% eligibility). In |
|
reference to the Like New
Replacement scheduled fro 2006-2007, roof replacement |
|
is not required to qualify a project
for Like - New status. |
|
|
Escalation (other) is calculated at
5% per year. |
|
|
|
|
|
|
Est. Cost |
|
273,000 |
|
Est Reimb (62.56%) |
(85,394) |
|
Net Cost |
|
187,606 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|