Capital Improvement Plan              
    FY2006-2007 through FY2013-2014              
                   
Department/Division:   Board of Education/Keeney              
                   
Project Name:   Like - New Renovation              
                   
Funding Source:   Future Bond              
                   
Project Description & Purpose:   Update entire facility to meet current ADA and/or Least Restrictive Environment (LRE)              
    requirements              
                   
Project   Financing Schedule
                   
    2006-2007 2007-2008 2008-2009 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014
                   
Planning & Engineering                 526,964
                   
Property Acquisition                  
                   
Construction                 11,166,608
                   
Equipment                  
                   
Other                 351,308
                   
Total   0 0 0 0 0 0 0 12,044,880
Justification/Comments: All codes addressed in conjunction with renovation to "Like New" condition.  For listing of
specific items, see attached excerpt from K-12 Facilities Study completed to Jeter, Cook & 
Jepson, June 20, 2002 (Items marked 1.x).  Costs estimated at $35 sq/ft of existing facility,
 no expansion assumed.  Escalation (Other) calculated at 5% per year.
Project also to address the following LRE items noted on prior capital improvement plan:
Electric door opener
Changing Table & Hoyer Life
1 8x8' Handicapped Access Restroom
Wheelchair Life for stage Access      
Est. Cost     12,044,880
Est Reimb (62.56%) (7,535,277)
Net Cost       4,509,603