Capital Improvement Plan |
|
|
|
|
|
|
|
| |
|
FY2006-2007 through FY2013-2014 |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Department/Division: |
|
Board of Education/Keeney |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Project
Name: |
|
Like - New Renovation |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Funding
Source: |
|
Future Bond |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Project
Description & Purpose: |
|
Update entire facility to meet current ADA and/or Least
Restrictive Environment (LRE) |
|
|
|
|
|
|
|
| |
|
requirements |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Project |
|
Financing Schedule |
| |
|
|
|
|
|
|
|
|
|
| |
|
2006-2007 |
2007-2008 |
2008-2009 |
2009-2010 |
2010-2011 |
2011-2012 |
2012-2013 |
2013-2014 |
| |
|
|
|
|
|
|
|
|
|
| Planning
& Engineering |
|
|
|
|
|
|
|
|
526,964 |
| |
|
|
|
|
|
|
|
|
|
| Property
Acquisition |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Construction |
|
|
|
|
|
|
|
|
11,166,608 |
| |
|
|
|
|
|
|
|
|
|
| Equipment |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Other |
|
|
|
|
|
|
|
|
351,308 |
| |
|
|
|
|
|
|
|
|
|
| Total |
|
0 |
0 |
0 |
0 |
0 |
0 |
0 |
12,044,880 |
|
| Justification/Comments: |
|
All codes addressed in conjunction
with renovation to "Like New" condition. For listing of |
|
specific
items, see attached excerpt from K-12 Facilities Study completed to Jeter,
Cook & |
|
Jepson, June 20, 2002 (Items marked
1.x). Costs estimated at $35 sq/ft of
existing facility, |
|
no expansion assumed. Escalation (Other) calculated at 5% per
year. |
|
|
|
Project also to address the
following LRE items noted on prior capital improvement plan: |
|
|
Electric door opener |
|
|
Changing Table &
Hoyer Life |
|
|
1 8x8' Handicapped Access
Restroom |
|
|
Wheelchair Life for stage
Access |
|
|
|
|
|
|
|
Est. Cost |
|
12,044,880 |
|
|
|
Est Reimb (62.56%) |
(7,535,277) |
|
|
|
Net Cost |
|
4,509,603 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|