Capital Improvement Plan |
|
|
|
|
|
|
|
| |
|
FY2006-2007 through FY2013-2014 |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Department/Division: |
|
Board of Education/Martin |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Project
Name: |
|
Like - New Renovation |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Funding
Source: |
|
Future Bond |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Project
Description & Purpose: |
|
Renovate entire facility to certified 20-year useful life |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Project |
|
Financing Schedule |
| |
|
|
|
|
|
|
|
|
|
| |
|
2006-2007 |
2007-2008 |
2008-2009 |
2009-2010 |
2010-2011 |
2011-2012 |
2012-2013 |
2013-2014 |
| |
|
|
|
|
|
|
|
|
|
| Planning
& Engineering |
|
|
|
|
|
|
1,730,570 |
|
|
| |
|
|
|
|
|
|
|
|
|
| Property
Acquisition |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| Construction |
|
|
|
|
|
|
5,445,175 |
|
|
| |
|
|
|
|
|
|
|
|
|
| Equipment |
|
|
|
|
|
|
333,000 |
|
|
| |
|
|
|
|
|
|
|
|
|
| Other |
|
|
|
|
|
|
915,235 |
|
|
| |
|
|
|
|
|
|
|
|
|
| Total |
|
0 |
0 |
0 |
0 |
0 |
8,423,980 |
0 |
0 |
|
| Justification/Comments: |
|
Addresses building, fire, health and
safety code issues. Includes all
aspects of |
|
|
construction
and FFE. Excludes ADA code
issues. Costs estimated at $165 sq/ft
of |
|
existing
facility, no expansion assumed.
Separate roof replacement cost listed as |
|
equipment. Excalation (other) calculated at 5% per
year. |
|
|
|
Project also to address the
following items noted on prior capital improvement plan: |
|
|
Window replacement |
|
|
Electrical upgrade |
|
|
|
|
|
Install sprinkler |
|
Est. Cost |
|
8,423,980 |
|
Replace 1 H.B. Smith
boiler (1968) |
|
Est Reimb (62.56%) |
(5,270,042) |
|
Rebuild unit ventilators |
|
Net Cost |
|
3,153,938 |
|
Roof Replacement |
|
|
|
|
|
Air conditioning in media
center |
|
|
Classroom furniture |
|
|
|
|
|
|
|
|
|
|
|