Capital Improvement Plan              
    FY2006-2007 through FY2013-2014              
                   
Department/Division:   Board of Education/Nathan Hale              
                   
Project Name:   Like - New Renovation              
                   
Funding Source:   Future Bond              
                   
Project Description & Purpose:   Renovate entire facility to certified 20-year useful life              
                   
Project   Financing Schedule
                   
    2006-2007 2007-2008 2008-2009 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014
                   
Planning & Engineering     2,378,772            
                   
Property Acquisition                  
                   
Construction     7,579,026            
                   
Equipment                  
                   
Other     396,462            
                   
Total   0 10,354,260 0 0 0 0 0 0
Justification/Comments: Addresses building, fire, health, and safety code issues.  Includes all aspects of
construction and FFE.  Excludes ADA code issues.  Costs estimated at $165 sq/ft of existing
facility, no expansion assumed.  Excalation (Other) calculated at 5% per year.
Project also to address the following items noted on prior capital improvement plan:
Window replacement      
Electrical upgrade Est. Cost    10,354,260
Conversion of airshaft space to additional storage Est Reimb (62.56%) (6,477,625)
Sprinkler installation in 1973 addition Net Cost      3,876,635
Air conditioning in media center      
Replace 2 Pacific Steam Boilers (Original 1921)
Rebuild top 3' of 45' chimney
Fat, Oil & Grease (FOG) separator (pending legislation)
Classroom furniture