Capital Improvement Plan              
    FY2006-2007 through FY2013-2014              
                   
Department/Division:   Board of Education/Waddell              
                   
Project Name:   Electrical Upgrade              
                   
Funding Source:   Future Bonds              
                   
Project Description & Purpose:   Upgrade electrical service to accommodate expanded use of technology              
                   
Project   Financing Schedule
                   
    2006-2007 2007-2008 2008-2009 2009-2010 2010-2011 2011-2012 2012-2013 2013-2014
                   
Planning & Engineering                  
                   
Property Acquisition                  
                   
Construction     60,000            
                   
Equipment                  
                   
Other                  
                   
Total   0 60,000 0 0 0 0 0 0
Justification/Comments: