Manchester Public Schools   Capital Improvement Plan     2006-2007 through 2013-2014                  
                         
SCHOOL PROJECT     2006/07 2007/08 2008/09 2009/10 2010/11 2011/12 2012/13 2013/14 FUNDING SOURCE
Washington Elevator Cylinder     40,000               Operating Bud
Washington Like New Renovation         13,563,960           Future Bond
                         
  Totals      $                40,000  $                         -  $            13,563,960  $                         -  $                      - $0 $0 $0  $         13,603,960
  Estimated Reimbursements (62.56%)     0 0 (8,485,613)   0 0 0 0  $         (8,485,613)
  Net Cost to Manchester     40,000 0 5,078,347 0 0 0 0 0  $          5,118,347